5) Use this information to answer the following questions: Beavis Construction Company was the low b
5) Use this information to answer the following questions:
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below:
2020 2021
Costs incurred during the year $450,000 $1,100,000
Estimated costs to complete 1,050,000 0
Billings during the year 400,000 1,400,000
Cash collections during the year 300,000 1,500,000
Assume that Beavis recognizes revenue upon completion of the project. Required: Compute the amount of gross profit recognized during 2020 and 2021.