A medium-size municipality plans to develop a software system to assist in project selection during
A medium-size municipality plans to develop a software system to assist in project selection during the next 10 years. A life-cycle cost approach has been used to categorize costs into development, programming, operating, and support costs for each alternative. There are three alternatives under consideration, identified as A (tailored system), B (adapted system), and C (current system). Find the annual worth of life-cycle cost for the best alternative at 8% per year.
Alternative
Component
Cost
A
Development
$925,000 now, $370,000 years 1–4
Programming
$925,000 now, $740,000 years 1, 2
Operation
$185,000 years 1–10
Support
$185,000 years 1–5
B
Development
$185,000 now
Programming
$370,000 year 0, $185,000 years 1–3
Operation
$370,000 years 1–10
Support
$370,000 years 1–10
C
Operation
$925,000 years 1–10