Assignment: The Manchester United Soccer Tournament project team
Assignment: The Manchester United Soccer Tournament project team (Review Manchester United case at the end of Chapter 4; page 126) has identified the following potential risks to their project:
- Referees failing to show up at designated games.
- Fighting between teams.
- Pivotal error committed by a referee that determines the outcome of a game.
- Abusive behavior along the sidelines by parents.
- Inadequate parking.
- Not enough teams sign up for different age brackets.
- Serious injury.
Risk Identification, Assessment and Mitigation
Question: How would you recommend that they respond (i.e., avoid, accept, …) to these risks and why? Be sure to provide each event and a response along with a contingency for each event.