cobit identifies 34 it processes and a high level approach to control over these processes the following is the process description of po10 manage projects

Required
The following items, in random order, are the outcome measures and performance indicators shown for PO10 “Manage Projects.” Classify each item as an outcome measure or performance indicator.
1. Percent of projects following project management standards and practices
2. Percent of certified or trained project managers
3. Percent of projects on time and on budget
4. Percent of projects meeting stakeholder expectations
5. Percent of projects receiving post implementation reviews
6. Percent of stakeholders participating in projects (involvement index)