Pinacle Corp. budgeted $255,590 of overhead cost for the current year. Actual overhead costs for the
Pinacle Corp. budgeted $255,590 of overhead cost for the current year. Actual overhead costs for the year were $232,640. Pinacle's plantwide allocation base, machine hours, was budgeted at 50,170 hours. Actual machine hours were 52,360. A total of 103,940 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for the current year is:
a.$2.24 per machine hour
b.$4.64 per machine hour
c.$5.09 per machine hour
d.$2.46 per machine hour