project management the company stc
ProjectLibre:
This is an opportunity to master a project scheduling tool. In this assignment, you will learn how to install the software and create a simple project plan. The project that you will create is detailed in the assignment document. You can use MS Project or ProjectLibre: http://www.projectlibre.org/ (PC and MAC) –
Both software have the same interface and functionality. Please do NOT go with paid cloud version. ï‚·
Refer to the following links for yours first steps in project scheduling:
Tutorial Part 1: Creating your first project
– see http://project-management.com/projectlibretutorial-part-1/
-YouTube Video:
Good luck
|
Rubric for Group Project |
|
|
Performance Criteria |
Score |
|
MS Project file with project name |
1 |
|
Calendar with Project name |
1 |
|
Specifying working hours according to project plan |
1 |
|
Friday and Saturday are weekends |
1 |
|
At least 2 exceptions and specified in the report |
1 |
|
At least 3 work resource |
1 |
|
At least 2 material resource |
1 |
|
At least 2 cost resource |
1 |
|
At least 4 phases |
1 |
|
At least 2 tasks in each phase |
1 |
|
Each task has to have duration, start, resource accurate |
1 |
|
At least 9 tasks have predecessors |
1 |
|
Lag and Lead time |
1 |
|
Each task has to be indented with its belonging phase1 |
1 |
|
Set the task mode to all tasks to auto schedule. |
1 |
|
at least 4 tasks to be milestone. |
1 |
|
a note in every phase of your project |
1 |
|
Change the type of dependency of one of the tasks |
1 |
|
Assign Resources to the Tasks. |
1 |
|
Show overallocation using resource graphs |
1 |
|
critical pathbefore levelling |
1 |
|
level the resources |
1 |
|
Set the baseline |
1 |
|
tracking of at least 5 tasks of your project (at least one of them to be 100%) |
1 |
|
tracking column and cost column |
1 |
|
Cost column has to have values |
1 |
|
weekly meeting for your team members and moves it to the top of the Gantt Chart |
1 |
|
Reports from the Dashboard |
1 |
|
Project Statistics |
1 |
|
Submission of project plan |
1 |
|
Cover page for the report include IDs and names |
1 |
|
Report is comprehensive, detailed and clear enough or not (snapshots after answering each question) |
1 |
|
Times New Roman and 12 pt |
1 |
|
The total * 9 /33 to get grade out of 9 |
7.00 |
|
Project Logic 1 mark |
1.5 |
|
Completion of the project in the class 2 marks |
1.5 |
|
Project grade to get grade out of 10. |
10.00 |