The Forging Department accepted Job 507 on May 15th to make 1,000 widgets. To complete the job, they
The Forging Department accepted Job 507 on May 15th to make 1,000 widgets. To complete the job, they requisitioned 2,100 sheets at $2.10 per sheet and 3,150 grommets at $0,51 per set. The cost driver that the Forging Department uses is drop-forge strokes which are counted on a machined mounted counter. $4.52 is applied as overhead for each drop-forge stroke. Additionally, $425 of overhead is applied to each job due to setup and teardown. Direct labor is $25.20 per hours for the machine operator and $16.30 for machine loader. The job required 29 hours of labor by the team. When the job was complete Job 507 was transferred to Finished Goods Inventory (FGI). When the job was transferred 60 sheets were returned unused to raw material inventory, 95 grommets sets were returned, and there were 3,115 strokes on the counter. Journalize all events depicted as of May 15th.