VILLANOVA UNIVERSITY – LEAN SIX SIGMA MASTER BLACK BELT (LSSMBB) Test 1

Week Two (2) – Test One (1).doc

  VILLANOVA
UNIVERSITY – LEAN SIX SIGMA MASTER BLACK BELT (LSSMBB)


  WEEK TWO (2) – TEST ONE
(1)

Question 1:The person most likely to be the
resource supporter who negotiates issues and works to  ensure handoffs is

A

The
Master Black Belt

B

The
Champion or Sponsor

C

The
Black Belt

D

The
Process Owner

Question 2:During the Improve phase of DMAIC,
the Master Black Belt is likely to be doing which of 
the following with Black Belts?

A

Reviewing
lessons learned

B

Exploring
statistical methodologies

C

Exploring
ROI alternatives

D

Reviewing
data gathering plans

Question 3:When doing a force field analysis,
both problems and opportunities can also be identified 
as
a driving force for change.

A

True

B

False

Question 4:The ideal communications strategy for
stakeholders will ____________________.

A

Get
the right information to the right people at the right time

B

Be
proportionate to the level of stakeholder interest

C

Be
proportionate to the level of stakeholder involvement

D

Be
proportionate to the level of stakeholder influence

E

Eliminate
requests for changes later in the project

Question 5:Which of the following are financial
metrics that can impact the implementation 
of your Lean Six Sigma Program?

A

Lean
Six Sigma programmatic return on investment

B

Individual
project return on investment

C

Organizational
financial metrics

D

Company
bottom line

E

All
of the above

F

None
of the above

Question 6:You have been asked to manage a
project to upgrade the software that call center  employees
use to answer customer questions. Which one of the following would be the
external 
stakeholder in this project?

A

Customers

B

Call
center staff

C

Human
resources department

D

Legal
department

Question 7:In order to minimize resistance later
in a Lean Six Sigma project and create “buy-in,” 
the Master Black Belt should encourage Black Belts to use what tool
earlier in the project?

A

Criteria
Based Decision Matrix

B

Gantt
Chart

C

Stakeholder
Analysis

D

Charter

Question 8:What are the three primary
characteristics of a stakeholder?

A

Informed,
involved, influential

B

Involved,
important, influential

C

Interested,
involved, influential

D

Active,
important, motivated

Question 9:A key leadership practice for Master
Black Belts to embrace is to

A

Help
others deal with the current state

B

Help
others break from the past

C

Communicate
compelling reasons

D

Both
B and C

Question 10:Which approach shows a balance
between a concern for people and a concern for 
production?

A

Autocratic

B

Democratic

C

Behavioral

D

Lassez-faire

Question 11:What is the best strategy for high
influence/low interest stakeholders?

A

Manage
them closely

B

Keep
them well-informed

C

Monitor
them periodically

D

Keep
them satisfied

Question 12:The primary goal of analyzing project
stakeholders is to

A

Determine
the best communications strategy

B

Understand
their relative importance to the project

C

Determine
where their interests agree or conflict

D

Map
the political terrain and how to navigate it

Question 13:One of the tools that the Master
Black Belt should ensure is used to help move a team toward 
goal completion and best help minimize conflict is

A

Role
and Responsibility Matrix

B

Network
Schedules

C

Gantt
Charts

D

Risk
Management Plans

Question 14:What type of change is seen as a
large improvement?

A

Transformational

B

Incremental

C

Logical

D

Itemized

Question 15:Key objectives of the processes to
develop the project team include

A

Ensuring
that the project team has smooth entry and exit throughout the project’s
life cycle to minimize the overall risk level on the project

B

Increasing
participation in the activities outlined in the communications plan and
scheduling activities to offload the team leads and PM

C

Improving
skills of team members and amending levels of trust and cohesiveness to
achieve better productivity through greater teamwork

D

Reducing
the possibility of stakeholder complaints by assigning each key stakeholder
a main team member point of contact to manage communications

  Question 16:One of the biggest resistance factors blocking implementation of
competitive intelligence 
and benchmarks is

A

Lack
of knowledge by Master Black Belts

B

Factors
associated with a learning organization

C

The
Not-Invented-Here (NIH) syndrome

D

Forces
of change

Question 17:Which type of leader relies on
legitimate, reward, and coercive power?

A

Autocratic

B

Democratic

C

Behavioral

D

Lassez-faire

Question 18:When coaching and educating Black
Belts concerning the Cost of Poor Quality, the 
Master Black Belt needs to direct attention to which of the following
items?

A

Assets,
Liabilities, and COGS

B

Profits,
Expenses, and Revenues

C

Number
of Incidents, Actual Labor Cost, Material Cost, and Multiplication

D

Number
of Defects, Variation, and Control Limits

Question 19:Key process steps in successfully
selecting projects include

A

Identifying
your current state

B

Developing
criteria for consideration

C

Developing
a list of projects based on pain, goals

D

All
of the above

Question 20:Which one of the following is the
most important reason for analyzing stakeholders?

A

To
determine the best communications strategy for them

B

To
understand their needs and expectations

C

To
manage their expectations

D

To
determine which metrics are most appropriate